COCESNA REHABILITATES NAVIGATION SYSTEMS, RAMÓN VILLEDA MORALES AIRPORT, SAN PEDRO SULA

On February 13, 2021, the COCESNA laboratory plane completed the commissioning of the air navigation systems of the Ramón Villeda Morales International Airport in San Pedro Sula. An inter-institutional team of professionals worked, continuously and tirelessly, during 3 intense months of work, in the recovery of the systems, damaged by the floods produced by hurricanes…

COCESNA FINALIZED STUDIES ON THE INFRASTRUCTURE IMPROVEMENT PROJECT AT THE COSTA RICA REGIONAL OFFICE

Last December 2020, COCESNA successfully concluded the studies included in the project “Improvements to CR Infrastructure, 2020”, which were intended to serve as the basis for the design of the expansion of the Costa Rica Station building and the reinforcement of the radar tower for the future purchase and installation of a radome. The contracting…